Bloomfield High School
Project Team
Structural Engineer: GM2 Associates, Inc.Owner: Town of Bloomfield
Architect: Tai Soo Kim Partners
General Contractor: Newfield Construction
Steel Joist Manufacturer: Canam
Steel Detailer: Joseph Perri
Steel Fabricator: Shepard Steel
Steel Erector: Action Steel, LLC
Project Type: Non-Industrial
Project Description
New library-media center for Bloomfield High School in Bloomfield Connecticut. The architect and school system requested an open, inviting space to create an exciting learning environment in the library-media center. What Makes This Project Interesting
The exposed and highlighted steel roof joists and structural steel. CANAM was the only joist manufacturer that would manufacturer LH series joist with round web members preferred by the architect for a clean appearance. The north facing full height glass wall looking out on to the courtyard with up-turned roof & the use of wood planking in the ceiling enhance the space.Advantages Of The Chosen Structural System
The architect wanted an economical, open roof framing system for the media center that would let in a maxiumum amount of light from the glass wall and create a very open, exposed environment.Project Scope
Additions and renovations to an existing high school including the library-media center, an auditorium stage addition, two entrance additions and extensive interior modifications.Project Details
Project Construction Cost: $22 millionJoist cost, including fabrication and erection: approx. $40,000
Size (square feet): 176,000
Roof area using joists (square feet): 6,800
Joist area (square ft.): 6,800
Joist engineering to delivery (# days): approx. 60 day
Joist erection (# days): 3 days